Home / Opportunities / Opportunity
PROCUREMENT OPPORTUNITY

OLE Monitoring for Class 730

WM TRAINS LIMITED · Preliminary market engagement notice on Find a Tender

Tender information last checkedLast checked 6 Oct 2026, 13:32.

Opportunity overview

General Information & Purpose of Engagement WM Trains Ltd is undertaking this Preliminary Market Engagement (PME) in accordance with the Procurement Act 2023 to engage the market regarding the supply and deployment of Overhead Line Equipment (OLE) Remote Condition Monitoring (RCM) systems across its Class 730/0 fleet. WM Trains currently operates eight OLE monitoring systems fitted to its Class 350 fleet, delivered via Transmission Dynamics and funded through an asset owner initiative with Angel. This legacy deployment relies on an established, proprietary front-end user interface and database accessed collaboratively by WM Trains, Network Rail, and fleet maintainers to safeguard infrastructure and maintain operational continuity. To enhance the coverage of its electrified routes, WM Trains requires an additional six monitoring systems for the Class 730/0 fleet. WM Trains considers that procuring an alternative, non-integrated solution would create fragmented operational dashboards, split data streams, and cause disproportionate technical difficulties in maintenance and real-time operations. Consequently, the core purpose of this PME is to directly test the market to establish whether any economic operator can realistically deliver the required functionality and integrate seamlessly with the existing proprietary setup without introducing disproportionate technical and operational difficulties. If the market engagement confirms that no compatible alternative can achieve this integration, WM Trains intends to formalise a direct award pursuant to Schedule 5, Paragraph 7 of the Procurement Act 2023 (Section 41 - Direct award in special cases: Additional or repeat goods, services or works). Key Scope Overview & Technical Constraints The planned requirement is strictly for the supply of OLE remote camera monitoring (RCM) and wireless accelerometer hardware, alongside the ongoing SaaS analytics subscription and the necessary engineering/design documentation. The physical installation and fitment to the Class 730/0 fleet will be undertaken separately by the fleet maintainer/OEM acting as the asset design authority. To satisfy operational, safety, and regulatory requirements, any proposed system must meet the following mandatory criteria: 1. Database & System Integration: All data generated by the Class 730 OLE systems must integrate fully and directly into the existing Class 350 OLE monitoring database. 2. Unified Front-End User Interface: The solution must provide a single, common front-end interface that aligns RCM imagery and sensor analytics to deliver real-time combined analytics throughout train operation, avoiding fragmented software suites. 3. Autonomous Defect Detection: The RCM system must autonomously identify and report dynamic OLE conditions, degradation, and infrastructure defects to designated stakeholders, with specific capability to identify and report on faulty dropper wires. 4. 5G Data Transmission: The solution must enable remote collection, processing, high-speed transfer, and review of dynamic OLE monitoring data utilising 5G capability. 5. Camera & Environmental Resilience: The camera system must be self-cleaning to prevent data and evidence loss, include a proven method for low-light conditions, and require no regular roof access for maintenance. 6. Physical & Systems Vehicle Integration: Roof-mounted equipment must be designed specifically for the Class 730 profile while strictly minimising physical and electrical integration into the host train network. 7. Rolling Stock Safety & Standards: The installation must fully comply with all relevant rolling stock standards and legislation, and must not adversely affect vehicle safety, reliability, maintainability, gauging, fire performance, EMC compatibility, or passenger service operations. 8. Engineering Deliverables & Approvals: The supplier must deliver all design, installation, commissioning, acceptance, and handover documentation required by the Infrastructure Manager (Network Rail), the TOC (WM Trains), the Fleet Maintainer (e.g. Siemens), and the ROSCO. 9. Maintenance & Calibration: The supplier must provide clear, documented maintenance, calibration, and ongoing technical support requirements for the installed system. 10. Data Ownership & Governance: All operational, diagnostic, and raw condition data generated across the fleet must be jointly and unreservedly owned by WM Trains Ltd and Network Rail, with unrestricted sharing rights for designated maintainers. Scope Clarification: For the avoidance of doubt, this procurement relates strictly to OLE condition monitoring interoperability and ingestion into the established OLE analytics database. WM Trains is not seeking multi-system train integration and will not review proposals detailing the ingestion of unrelated rolling stock subsystems (such as onboard CCTV, PIS, or general telematics) into an OLE platform.

Classification

  • CPV60200000 — Railway transport services

Lots

  • Lot 1Value not stated

Documents and notices

Published notice details

Additional information from the published procurement release. Fields appear only when supplied by the source; check the original notice and tender documents before acting.

Scope, procedure and submissions

Id
ocds-h6vhtk-06a0bb
Main Procurement Category
services
Above Threshold
Yes
Status
planned

Legal basis

Id
2023/54
Scheme
UKPGA

Special regime

utilities

Communication

Future Notice Date
30 Oct 2026, 23:59

Amendments

Entry 1
Description
Corrected PME consultation period from 17/10 to 16/10
Id
094194-2026

Lots and requirements

Entry 1
Id
1
Has Renewal
Yes
Status
planned

Suitability

Sme
Yes

Contract period

Starts
1 Jan 2027, 00:00
Ends
31 Dec 2031, 23:59
Max Extent Date
31 Dec 2034, 23:59

Items and delivery

Item 1
Id
1
Related Lot
1

Additional Classifications

Entry 1
Scheme
CPV
Id
60200000
Description
Railway transport services

Delivery locations

Entry 1
Region
UKC
Country
GB
Country Name
United Kingdom
Entry 2
Region
UKD
Country
GB
Country Name
United Kingdom
Entry 3
Region
UKE
Country
GB
Country Name
United Kingdom
Entry 4
Region
UKF
Country
GB
Country Name
United Kingdom
Entry 5
Region
UKG
Country
GB
Country Name
United Kingdom
Entry 6
Region
UKH
Country
GB
Country Name
United Kingdom
Entry 7
Region
UKI
Country
GB
Country Name
United Kingdom
Entry 8
Region
UKJ
Country
GB
Country Name
United Kingdom
Entry 9
Region
UKK
Country
GB
Country Name
United Kingdom

Planning and budget

Milestones

Entry 1
Id
engagement
Type
engagement
Description
Market Engagement Process & Submission Instructions Suppliers capable of meeting the technical constraints and demonstrating true cross-platform integration are invited to participate under the following procedure: • Expression of Interest (EOI): Interested suppliers must email procurement@wmtrains.co.uk no later than 9th October using the mandatory subject line: OLE Monitoring for Class 730 - PME Expression of Interest • Engagement Pack Distribution: Upon receipt of a valid EOI, suppliers will be issued the complete Technical Evaluation Pack and Response Questionnaire. • Evidence Submission: Participating suppliers must complete and return the provided questionnaire in full. Submissions must explicitly address the integration challenge by responding to the structured criteria, which include: Section A: Technical proposals for direct database integration and analytics standardisation. Section B: Proof of core technical compliance, hardware constraints, and 5G architecture. Section C: Acceptance of WM Trains' mandatory data ownership and governance model. Section D: Verifiable commercial case studies demonstrating successful integration across proprietary third-party railway platforms in a live operational environment. • Clarifications & Final Submissions: Any written questions or clarifications regarding the requirements must be sent to the contact email no later than 9th October Final PME questionnaire responses must be submitted by 16th October. Procurement Transparency & Engagement Rules • Assessment of Market Capability: Submissions will be evaluated by WM Trains' technical and commercial project team. The outcomes will inform whether a competitive procurement procedure is feasible or if a justification for a Direct Award under Schedule 5, Paragraph 7 of the Procurement Act 2023 is confirmed. • Clarifications & Consolidated Responses: WM Trains Ltd will not enter into bilateral dialogue or provide bespoke feedback on individual submissions. WM Trains reserves the right to issue consolidated, anonymised responses to clarification queries to all participating suppliers where appropriate. • Non-Commitment & No Competitive Advantage: Participation in this preliminary market engagement is entirely voluntary and conducted at the supplier's own cost. Participation does not confer any advantage, preference, or priority in any subsequent procurement procedure. The publication of this PME notice does not commit WM Trains Ltd to conduct a tender or proceed with any contract award.
Due
16 Oct 2026, 23:59
Status
scheduled

Documents

Entry 1
Id
094194-2026
Document Type
marketEngagementNotice
Notice Type
UK2
Description
Preliminary market engagement notice on Find a Tender
Published
6 Oct 2026, 11:52
Format
text/html

Buyer, suppliers and contacts

Organisation 1
Name
WM TRAINS LIMITED
Id
GB-COH-12545250

Identifier

Scheme
GB-COH
Id
12545250

Additional Identifiers

Entry 1
Scheme
GB-PPON
Id
PYZB-7245-XPRH

Address

Street Address
134 Edmund Street, 2nd Floor
Locality
Birmingham
Postal Code
B3 2ES
Country
GB
Country Name
United Kingdom
Region
UKG31

Contact

Roles

buyer

Details

Classifications

Entry 1
Scheme
UK_CA_TYPE
Id
publicUndertaking
Description
Public undertaking

Recorded locations

  • Buyer location · Birmingham · UKG31 · B3 2ES · United Kingdom
  • Delivery location · UKC · United Kingdom
  • Delivery location · UKD · United Kingdom
  • Delivery location · UKE · United Kingdom
  • Delivery location · UKF · United Kingdom
  • Delivery location · UKG · United Kingdom
  • Delivery location · UKH · United Kingdom
  • Delivery location · UKI · United Kingdom
  • Delivery location · UKJ · United Kingdom
  • Delivery location · UKK · United Kingdom

Notice and amendment history

5 published notice versions reviewed by ProcuraAxis.

5 VERSIONS
  1. 047700-2026Pipeline notice on Find a Tender ·
  2. 081212-2026Pipeline notice on Find a Tender ·
  3. 093319-2026Pipeline notice on Find a Tender ·
  4. 093967-2026Preliminary market engagement notice on Find a Tender ·
  5. 094194-2026Preliminary market engagement notice on Find a Tender ·

PROCURAAXIS ANALYSIS

ProcuraAxis Analysis

Our approved analysis of the opportunity appears below the official tender information.

ANALYSIS PREVIEW

Opportunity intelligence at a glance

Early-stage preliminary market engagement (not an open bid) for six OLE remote condition monitoring systems for WM Trains’ Class 730/0 fleet. The planned supply includes remote cameras, wireless accelerometers, SaaS analytics and engineering documentation, with full integration into the existing Class 350 proprietary OLE monitoring database and user interface.

Who this may suit

Best suited to suppliers able to provide interoperable OLE monitoring hardware and SaaS analytics that can integrate directly with WM Trains’ existing Class 350 OLE platform. Installation is excluded and will be undertaken separately by the fleet maintainer/OEM.

Key points identified

  • System integrationAll Class 730 OLE monitoring data must fully and directly integrate into the existing Class 350 OLE monitoring database.Evidence: “All data generated by the Class 730 OLE systems must integrate fully and directly into the existing Class 350 OLE monitoring database.”
  • Unified user interfaceA single common front end must combine RCM imagery and sensor analytics in real time.Evidence: “The solution must provide a single, common front-end interface that aligns RCM imagery and sensor analytics to deliver real-time combined analytics.”
  • Defect detectionSystem must autonomously identify and report dynamic OLE conditions, degradation and defects, including faulty dropper wires.Evidence: “The RCM system must autonomously identify and report dynamic OLE conditions, degradation, and infrastructure defects... capability to identify and report on faulty dropper wires.”
95% approved-analysis confidence10 supplier criteria identified4 risks or unknowns

SOURCE AND FRESHNESS

Traceable procurement data

Source
Find a Tender
Notice reference
094194-2026
OCID
ocds-h6vhtk-06a0bb
First published
26 Aug 2026
Last checked
6 Oct 2026, 13:32
Notice versions reviewed
5

HOW THIS WAS PREPARED

Approved, evidence-bound analysis

ProcuraAxis structures information found in published procurement records, checks the result for consistency and publishes only approved analysis. Confidence describes the completeness and consistency of the available source information; it is not a guarantee of eligibility or contract award.

Analysis status
Approved for publication
Analysed
6 Oct 2026
Read the analysis methodology →