Opportunity overview
The University of Edinburgh has appointed a single supplier as Main Contractor to undertake the construction of the LARIF Phase 2a project. The contract commencement date is 28th October 2025, for a period of 90 weeks, involving a 3-week mobilisation period, 35-week construction period, and 52-week defects liability period.
Awarded to
Amounts belong to published awards or contracts. Where several suppliers share one value, it is labelled as shared and is not a supplier-specific allocation.
Clark Contracts Limited
Matched by exact name
- Contract value
- £2.6m
- Awarded
- Not supplied
- Contract signed
- 28 Oct 2025
- Award ID
- 072953-2025-EC1044-1
- Status
- active
- Location
- Paisley, UKM, PA3 1RY, United Kingdom
Classification
- CPV45000000 — Construction work
- CPV45213240 — Agricultural buildings construction work
Lots
- The University of Edinburgh has appointed a single supplier as Main Contractor to undertake the construction of the LARIF Phase 2a project. The contract commencement date is 28th October 2025, for a period of 90 weeks, involving a 3-week mobilisation period, 35-week construction period, and 52-week defects liability period. The contract has been awarded following an openly advertised Restricted Procedure (two-stage tender process).£2m