UK Fusion Energy Ltd
Buyer information published with procurement notices.
- Published identifier
- GB-PPON PCRM-7973-DCBL
- Address
- Abingdon, UKJ14, OX14 3DB, United Kingdom
- First notice
- 14 Mar 2025
- Latest notice
- 2 Oct 2026
Published procurement activity · 128 tenders
Buyer information published with procurement notices.
The proposed scope under consideration comprises three principal areas: Cryogenic Plant; Cryogenic Distribution System; and Cryogenic User Integration. The STEP cryogenic system is intended to provide the cryogenic cooling infrastructure required to support major plant systems throughout the STEP Prototype Powerplant. Current c
This Notice aims to gather information from potential suppliers on capabilities and approaches in relation to UKFE’s proposed procurement for specialist analysis of future electricity systems, sources of value and electricity markets relevant to commercial fusion deployment. This is not a request for quotation but a preliminary
UKFE is running a procurement process to identify a suitably qualified Supplier for the provision of PLANC (Permitting, Licences, Authorisations, Notifications & Consent) Assurance. The appointed Supplier will provide an independent assurance service, principally as a 3rd Line Assurance function, delivering objective challenge a
To appoint an independent reviewer to undertake a comprehensive Board Effectiveness Review of the Board of UK Fusion Energy Ltd. The review will provide the Board with an objective assessment of its effectiveness, governance, decision-making and oversight, together with practical recommendations for continuous improvement. The r
The STEP programme aims to deliver a UK prototype fusion energy power plant in the 2040s and establish a credible pathway to the commercial deployment of fusion energy. United Kingdom Fusion Energy Ltd (UKFE Ltd) seeks to maximise the national and regional economic and industrial benefit of the STEP programme, in line with the s
UK Fusion Energy Ltd (UKFE) is seeking to appoint a supplier to undertake the concept design of a system capable of in-situ quantification of tritium retention within plasma-facing (first wall) materials for the Spherical Tokamak for Energy Production (STEP) programme. STEP is the UK's flagship fusion energy programme, sponsored
UKFE is seeking to appoint a suitable Supplier (an individual organisation or a consortium with a lead supplier) for a services contract to provide a study for concept designs of Heating, Ventilation and Air Conditioning (HVAC) within the Tokamak building to be built at West Burton Power Station. The study shall provide the tech
The STEP Fuel Cycle is the subsystem responsible for recovering, purifying and supplying tritium to the STEP fusion reactor. Tritium is present in a variety of forms, phases and compositions, including tritiated water. Vapour-phase electrolysis techniques such as solid-oxide electrolysis have been identified as a suitable techni
UKFE is seeking to progress the design and manufacturability of a novel transmission system that is planned to be integrated into the MAST-U EBW transmission line
MTC Industrial membership program is designed the Members designed from manufacturers, technology providers, SMEs, and large organisations together to collaborate on innovation, research, and industrial challenges. Membership supports MTC's Core Research Programme and gives organisations a voice in shaping future manufacturing t
Organisation details and tender classifications reflect information published by the original procurement sources. Similar buyer names are grouped only where an official identifier or compatible name and postcode provide a safe link.